Dam rehabilitation reports tested against gates, spillways and monitoring
A completion announcement should be checked against mechanical tests, civil defects, instrumentation and the operating team’s rea…
The people, projects and decisions building South Africa
Mpumalanga desk
Construction reporting from Mpumalanga.

A completion announcement should be checked against mechanical tests, civil defects, instrumentation and the operating team’s rea…

A national audit sample found delays, defects and commissioning failures across housing projects, including homes recorded as com…

The wind-energy facility near Bethal is the first phase of a planned 900MW renewable programme in Mpumalanga.

The scheme is designed to deliver 20 million litres a day to Thembisile Hani.

Municipal debt to water boards rose sharply as ageing networks continued to lose treated water. The pressure travels through the…

Registration of a builder and enrolment of a particular home are related but separate checks.

Municipalities reported expenditure and completion, but physical inspections repeatedly found delay, weak quality control and ass…

Participation targets deliver more value when packages, mentoring and payment are planned from tender stage.

Bulk services and site preparation are moving before the larger economic-development projects reach full construction.

Bulk water has been upgraded, electrical installation is under way and the site is established.

Bulk water, electricity and sewer designs are being finalised for the planned zone.

The programme raises capacity from 20 to 40 million litres a day.

Projects in Thembisile Hani, Mkhondo, Lekwa and Thaba Chweu show the range of infrastructure needed for reliable supply and sanit…

Capacity is being increased from four to 12 million litres a day.

The treatment process is intended to address metals associated with mining pollution.

The plant is being refurbished and expanded from 5.5 to 11 million litres a day.

The coordinated package targets sewage spills and unreliable water access.

The Mkhondo project pairs new treatment capacity with conveyance infrastructure.

The Amsterdam-area scheme combines storage with a long transmission pipeline.

Panels may be light individually, but arrays add permanent load, wind forces and concentrated reactions to an existing roof.