A project with several finish lines

The Giyani water programme is often described as if it were one construction contract with one completion date. Official records show a chain of dependent works: raw-water transfer, treatment capacity, boreholes, bulk pipelines, reservoirs, village reticulation and the final connections that make water available to households.

This matters because one component can be physically complete while communities remain outside the service. A functioning bulk line moves water across the system. It does not automatically prove that every downstream reservoir, reticulation network and household connection is complete, commissioned and supplied at adequate pressure.

The cost and delay record

The Auditor-General’s 2022-23 consolidated report used the Giyani project as an example of delayed infrastructure. The report says the project began in 2011 and had remained incomplete for more than a decade. It records an initial budget of R284 million, revised to R520 million in 2019 and to R767 million in 2020. At June 2023, the project was still incomplete.

Those figures relate to the project scope examined in that report. They should not be confused with the cost of every linked Giyani intervention announced later. The broader programme includes additional packages, contracts and implementing arrangements.

The audit report also recorded that the Special Investigating Unit was investigating the project. An investigation is not a finding of guilt against every participant. It does mean that cost changes, contracting decisions and responsibility for delay belong in the public record rather than being reduced to a single ceremonial completion.

What later records say was delivered

A Department of Water and Sanitation presentation to Parliament records that the 40.5-kilometre Nandoni-to-Nsami pipeline became functional in April 2023 and reached practical completion in December 2023. It says refurbishment of the Nsami water-treatment works was completed in June 2024.

The same official presentation describes the wider scope: a 1.5-megalitre-per-day wastewater treatment works, 154 boreholes, about 325 kilometres of pipeline and a 49-kilometre bulk pipeline. These components serve different purposes and were not all delivered on the same timetable.

By the department’s November 2025 update, the 325-kilometre service project was reported at 90.23% progress with a target of May 2026. That update is evidence of reported construction progress. It is not a household-level service audit.

The handover gap

The most important transition in a water project is often not visible in photographs. Once construction is complete, an operating authority must accept the asset, staff it, power it, maintain it, monitor water quality and manage the network. Reservoirs and village systems must be ready for the additional flow.

If downstream works lag, a completed bulk asset can have limited immediate effect. If municipal operating budgets, electricity supply, treatment chemicals, telemetry or repair teams are weak, the new infrastructure can also underperform after handover.

That is why “completed” should always be followed by another question: completed at which point in the water chain?

What a service test should measure

Project reporting usually measures kilometres laid, percentage construction progress and milestone dates. A service test needs different evidence: which villages receive water, how many households are connected, hours of supply, pressure, interruptions, tanker dependence, water-quality compliance and the date on which each service zone became operational.

A credible close-out report would connect those two sets of measures. It would show how a physical asset changed supply in defined communities and would identify where the chain is still incomplete.

The accountability questions

The documentary record leaves several questions that should be answered at contract and service-zone level. Which budget revisions were caused by scope changes, escalation, design development or delay? Which contracts are closed, which remain active and which are subject to claims? Which assets have been handed over, and to whom? Which villages still depend on interim supply? What operations funding is in place after construction?

Answers should be published with dates and named responsible institutions. Without that, announcements about bulk completion and public frustration about household supply can appear contradictory even when they describe different points in the same system.

How we reported this investigation

This investigation compares AGSA’s 2022-23 audit account with later Department of Water and Sanitation and parliamentary infrastructure records. We treated every date and percentage as a report by the issuing institution, not as independent site verification. The article distinguishes the audited historical package from later linked works and does not attribute wrongdoing to any individual or contractor.

What we will track next

The next useful update should connect physical progress to service performance. For Giyani water: the difference between a completed bulk line and water at the tap, that means identifying which assets are commissioned, who operates them, whether water-quality or effluent tests are current and how reliability is measured after handover. Published percentages are easier to assess when the reporting date, design capacity, actual flow and outstanding work appear together.

Readers should also look for power resilience, maintenance funding, trained operators and a defects process. Pipes, pumps, reservoirs and treatment units form one chain; completion of one component does not prove that the full service is working.